Month-by-month financials for the projects in your selection: what was invoiced, how much chargeable work was done, recovery and gross profit. The chart shows these by month, and the table lists them per project for the selected period.
There are two variations of this dashboard. Monthly Financials shows invoicing, chargeable work, recovery and gross profit. Monthly Financials | With Resourcing shows the same, and adds the charge planned in resourcing to the project table so you can compare the chargeable work recorded with the work planned.
Invoiced revenue comes from invoices, by invoice date (draft invoices excluded). Invoiced charge, mark-up/down, recovery, invoiced cost and gross profit cost come from transactions, by the date they were invoiced. Charge generated and cost incurred come from transactions, by the date the work was recorded.
In the With Resourcing variation, resourced charge comes from the resourcing planned for each project in the selected period. Every figure covers only the period you select (it is not a running total), and only current and past months are shown.
Note: We advise enabling only one variation of this dashboard. Enabling both adds duplicate Monthly Financials tabs to the Projects module.
How to use it
Choose the period with the Date, FY, FY Qtr and Month End filters.
Use the buttons and filters to change what's shown. See What changes the numbers on this page.
Understanding your data
Visuals
Invoiced Revenue & Charge Generated (chart)
Columns and lines by month for the selected period.
Visual type | On-screen name | How it's calculated |
Column | Invoiced Revenue | Adds up invoice amounts excluding tax, by invoice date. Draft invoices are excluded. |
Column | Charged Invoiced | Adds up the value of work with a status of Invoiced or Written off, by invoice date.
|
Column | Charge Generated | Adds up the value of all work recorded, by transaction date, counting only chargeable work.
|
Line | Recovery % | Revenue on transactions invoiced in the period divided by Invoiced Charge, both by invoice date.
|
Line | Gross Profit % | Invoiced Revenue minus standard cost by invoice date, divided by Invoiced Revenue.
|
Project table
One row per project (Project Number, Project Name), for the selected period. The ↗ link opens the project's Project Overview page in Synergy.
Both variations show these columns.
Visual type | On-screen name | How it's calculated |
Table | Invoiced Revenue | Adds up invoice amounts excluding tax, by invoice date. Draft invoices are excluded. |
Table | Invoiced Charge | Adds up the value of work with a status of Invoiced or Written off, by invoice date.
|
Table | Mark Up/Down | Adds up the mark-up or mark-down recorded on transactions in Synergy, excluding tax, by invoice date.
|
Table | Recovery % | Revenue on transactions invoiced in the period divided by Invoiced Charge, both by invoice date.
|
Table | Charge Generated | Adds up the value of all work recorded, by transaction date, counting only chargeable work.
|
Table | Invoiced Costs | Adds up the standard cost of work with a status of Invoiced or Written off, by invoice date. |
Table | Gross Profit | Invoiced Revenue minus standard cost by invoice date. |
Table | GP % | Invoiced Revenue minus standard cost by invoice date, divided by Invoiced Revenue.
|
Table | Cost Incurred | Adds up the standard cost of all work recorded, by transaction date. |
Resourcing columns (With Resourcing variation only)
Extra columns in the project table on Monthly Financials | With Resourcing, for the selected period.
Visual type | On-screen name | How it's calculated |
Table | Resourced Charge | The charge planned in resourcing for the project in the selected period. Each resourcing estimate's charge is spread evenly across the days it runs, and the weekdays in the period are added up.
|
Table | Variance | Charge Generated minus Resourced Charge.
|
Things to know
Internal and Non-billable Projects are excluded on this page. These are projects flagged as office projects in Synergy. This is separate from stages with the No Billing fee type.
The Fee Type filter excludes stages with the No billing fee type by default, and the Status Group and Status filters default to Active, Complete, On Hold and Pending Invoice. Change them to include other work.
Percentages are calculated from totals added together, not averaged.
All figures come from data entered in Synergy, so any corrections are made in Synergy.
What changes the numbers on this page
Type | Options available | Default |
Unit selection | Units, Thousands, Millions | Units |
Date hierarchy | FY, FY Qtr, Month, Week Ending, Week Start | Month |
Date filters | Date, FY, FY Qtr, Month End | FY: current period; FY Qtr: current period |
Status filters | Status Group and Status | Active, Complete, On Hold, Pending Invoice |
Fee Type filter | Stage fee types | All except No billing |
Filters | Account Manager, Primary Contact Name, Project Number Name, Project Salesperson, Project Director, RAG Level, Project Type, Cost Centre, Stage Manager, Status Group, Status, Fee Type, Office, Discipline, Project Manager (filters marked active only list active items only) | — |
Fixed filters | Current and past months only; Internal and Non-billable Projects excluded | Always applied |