In the Project > Plan > Schedule page, you can adjust the start and/or end dates for any project that is not marked as completed or unsuccessful in two ways.
- Drag either end of the row to the desired date 
- Click and move the entire row to a new date period. 
When you adjust the dates for a project in planning mode using either of the above methods, Synergy’s elastic planning means:
- Any affected child phases will adjust to reflect the new project date. 
- Any child stages will adjust to reflect the new project date. 
- Any child tasks will adjust to reflect the new project date. 
If you are in delivery mode, you cannot adjust the project start and/or end dates.