Skip to main content
All CollectionsSynergy HelpThe Planning Board
How do I change a project's date in the Schedule?
How do I change a project's date in the Schedule?
Updated over 3 years ago

In the Project > Plan > Schedule page, you can adjust the start and/or end dates for any project that is not marked as completed or unsuccessful in two ways.

  1. Resize the pill to a new date, by clicking on either end of the pill and moving it to a new date.

  2. Click and drag the entire row to a new date period.

When you adjust the dates for a project in planning mode using either of the above methods, Synergy’s elastic planning means:

  • Any affected child phases will adjust to reflect the new project date.

  • Any child stages will adjust to reflect the new project date.

  • Any child tasks will adjust to reflect the new project date.

If you are in delivery mode, you cannot adjust the project start and/or end dates but you can still drag the project to a new date period.

Did this answer your question?