Edition: Enterprise
User-level: Assistant Project Manager, Project manager, Director, Assistant Administrator, System Administrator
The following article will detail how to add a due date to a to-do in the project schedule in Synergy to keep track of when work needs to be complete.
1. From project Select the Project Menu > Plan > Schedule
2. Open up the corresponding stage, any to-dos added will be to the right of the task they were added against
3.Select the to-do you would like to edit from the right-hand pop-out menu.
4.You can add a due date from this side menu.
The purpose of the to-do due date is so it will appear on that day in the calendar view.
Tips!
By default, the due date of the to-do is the end date of its task.
Clicking out of the pop-up panel will save your changes.
Where to next?
What other features does this relate to?
Project Schedule, Kanban, Calendar View