Edition: Professional, Business (work breakdown only), Enterprise
User-level: Project Manager and higher access levels
Use custom colours to help easily identify stages, tasks and milestones within a project structure or to follow an industry framework such as RIBA (Royal Institute of British Architects).
Colours for these can be changed from the Schedule, Project Planning, Work Breakdown, and action panes by selecting a predefined colour using the Colour Picker.
Custom colours are applied at a project level, meaning all users will see the same colours that have been applied to a single project.
Custom colours for the planning board
Custom colours for the planning boards are enabled by default.
When the setting is enabled, stage, task, and milestone icon colours can be customised on the Planning Board and Project Schedules.
When the setting is disabled, the colour picker is hidden from the Planning Board and Project Schedule. The colour picker will still be accessible from action panes and the Work Breakdown.
To disable custom colours:
From the dashboard, select the main menu > Settings > Organisation > Configuration.
Untick 'Enable Colour Customisation' located at the bottom of the configuration page.
Click Save
Changing colours on the planning board
Use the following steps to change Stage, Task or Milestone icon colours on a project on the planning board:
Open the planning board and expand the project
Click on the stage, task or milestone icon to open the action pane.
Click the dot displayed near the stage, task or milestone name to access the colour picker.
Select a colour then click the save button at the bottom of the action pane.
The new colour is applied and will be displayed on the planning board.
Work breakdown
Custom colours can be selected for stages, tasks and milestones in the work breakdown using the same colour palette as the planning board.
Any changes made to stage, task or milestone colours in the work breakdown will be reflected on the same project when viewed from the project schedule or planning board.
When a stage colour is changed, any new tasks or milestones added to the stage after the change has been saved will be assigned the same colour. Existing tasks and milestones will retain their original colours.
To change a stage colour:
Edit the work breakdown
Click the dot to the left of the stage name to display the colour picker. The current colour is highlighted in the panel.
Click on a square in the colour picker to select a new colour. The colour picker will close and the new colour will be displayed.
Save the work breakdown
To change a task or milestone icon colour:
Edit the work breakdown
Expand a stage to view tasks and milestones
Click the dot to the left of the task name or milestone icon to display the colour picker. The current colour is highlighted in the colour picker.
Click on a square in the colour picker to select a new colour. The colour picker will close and the new colour will be displayed.
Save the work breakdown
Personalising your view
If you do not wish to see projects and custom-applied colours you can view the default Synergy colours. This doesn't affect customisations at the project level for other users.
To access this option from the planning board:
Click the gear icon at the bottom of the left menu pane
Slide the toggle to the left to disable your view of custom colours
3. Changing this option will only affect the Planning Board. Custom colours will still be shown on the work breakdown.
Planning Board Legend
When custom colours are enabled, a different legend is available to view on the planning board. This legend indicates the stylisation changes for the planning board pills when custom colours are in use.
When custom colours are turned off either from the organisation configuration page or from the menu pane on the planning board, the default legend will be shown.
Project schedule
Use the Colour Picker to change Stage, Task or Milestone icon colours.
The Colour Picker is accessed by clicking on a Stage, Task or Milestone icon from the menu pane.
The same functionality can be accessed by opening the Stage Resourcing action pane, clicking on the stage colour and selecting a new colour from the now open colour picker.
This same functionality is also applied to the Task and Milestone action panes panes.
Project templates
Custom colours can be used on project templates in the work breakdown and the project schedule.
These colours will be applied to any new projects created using that template or existing projects when a template is applied.