Can I View My Unearned Income Before Activating the Change?

Checking unearned income on projects

Updated this week

Edition: Enterprise

User-level: System Administrator, Assistant Administrator, Project Manager, Assistant Project Manager


If you need to balance your Complete % to what is in your accounting package/spreadsheet, you can do this by generating a report.

From Side Navigation, seIect Reports, then search for and run and run the Unearned income – by primary contact report.

If the amounts do not balance, you will need to go back to the stage(s) and move the slider to where it should be.

By default, this report is grouped by contacts and then projects. You will see which stages have been invoiced in the project drop-down. Like all reports, you can customise this view.

This is also the same report you will see if you generate a report from the configuration page.